September 2026
Here is the latest update from the ARAVITA construction site. 🏠Villas • 1BD - roof installation, under-slab first-fix MEP works and the fence base have been completed. • 2BD - under-slab first-fix MEP works have been completed and roofing works have commenced. • 4BD - the second-floor slab has been poured. Setting-out for the first-fix MEP works and construction of the fence base are underway. • 3BD - steel frame installation has been completed and setting-out for the first-fix MEP works is underway. • Concreting of four swimming pool structures has been completed. • Roofing works at all four mock-ups will be completed by the end of September. 👊Foundation Works • Earthworks for villas 49–56 have been completed. Preparations for foundation works are underway. • Earthworks continue across the entire project. ↗️Infrastructure • A room has been constructed for the project’s temporary 107-kW connection to the PLN grid. • A shipment of press fittings from China has arrived. Assembly of the villas’ water-supply manifold units will begin next week. • The road near villas 1–3 is being prepared for the installation of U-Ditch drainage channels. 📩We will continue to share further updates as construction progresses.
August 2026
ARAVITA | Construction Progress Update 🏗️ Here is the latest update from the ARAVITA construction site. 4-Bedroom Villa 🏠 • Steel frame installation is nearing completion. • Metal decking has been prepared. • Everything is ready for concreting the first-floor slab. • Concreting is planned for Friday or Saturday this week. 1- and 2-Bedroom Villas 🏘️ • Steel frames have been fully completed. • Pool reinforcement and utility installation have been completed across all three villas. • The next stage is concreting. 3-Bedroom Villas 🏗️ • Foundation footings have been concreted for one of the villas. Site Works 🚜 • Earthworks are actively underway for 9 swimming pools. • Once completed, pile installation for these villas will begin. • To increase the pace of construction, an additional 4 excavators and 4 trucks have been deployed. At the same time, our Sales Office is open 📍, where visitors can explore the project’s materials and key solutions, including marble, terrace and facade finishes, soffits, flooring, and roofing. We will continue to share updates as construction at ARAVITA progresses!
July 2026
📊 Construction Progress Report 📅 17.07.2026 ARAVITA: construction moves into its next phase 🏗️ Completed so far: — Concrete foundations for 1BR, 2BR and 3BR villas — done — Pool foundation MEP systems — installed — Steel frames for all villa types — fully fabricated and welded — Villa 4: earthworks complete, foundation works starting, part of the materials already purchased — Site fully prepared: perimeter fencing, lighting, and all MEP working documentation handed to production Quality control: — Fastener samples collected from several suppliers, hardness-tested to select the best partner for bulk procurement What's next: — Piling contractor mobilizes this Friday — kicking off the next foundation stage — Running foundation works in parallel is expected to cut the project timeline by roughly 4 months Equipment & infrastructure: — Two new excavators on site — a real boost to productivity — PLN contract signed for 107 kW — moving off diesel generators, lowering operating costs — CCTV already covers 20% of the site — investors will soon get personal camera access to their own villa Team expansion: a maintenance mechanic and two excavator operators hired; roofing, concrete, and MEP contractors finally confirmed. The site is fully equipped — active construction phase ahead.
June 2026
🏗️ ARAVITA | Report #6 | 01.07.2026 Here is the latest construction update for the ARAVITA project in Nusa Dua. Over the past two weeks, we have made significant headway and transitioned to active, large-scale works on site. 📌 Earthworks Construction has entered an active excavation phase. Heavy machinery is operating continuously on-site: excavators are digging foundation pits for the future villas and shaping the basins for the individual swimming pools. 📌 Surveying & Layout To ensure all structures are perfectly aligned and strictly match the project design, our surveying team is working on-site, setting the exact coordinates and laying out the axes for each villa. The surveyors work hand-in-hand with the excavator operators. This allows us to control elevations in real-time during excavation, ensuring pinpoint accuracy. 📌 Foundation Works In parallel, we have begun preparing the ground bases for the future villas. At this stage, our team is assembling and tying rebar cages, which will reinforce the concrete foundations. 📅 Our Plans We plan to fully complete all earthworks and foundation works by the end of September. This will allow us to proceed to the next major phase in October: constructing the villas' reinforced concrete structural frames.
May 2026
🏗️ ARAVITA | Report #6 | 21.05.2026 Sharing the current status of construction works on the Aravita Residence project. 📌 Sales Office Construction is ongoing. Marble work in the bathroom has been completed, floors are ready, and the drainage system has been installed. All finishing materials and engineering solutions match those that will be used in the project's villas: solid parquet flooring, natural marble, final electrical and water supply systems. The sales office is not a "temporary space" — it is the first real introduction to the quality standard of Aravita. 📌 Foundation Works Work on installing the foundations for the mockups is continuing. To date, 49 foundation footings have been completed for 3- and 4-bedroom units. Works are carried out in stages: concrete column footings → blinding layer → formwork installation → concreting of pedestals to design dimensions. Metal formwork is being used for the current cycle — a more precise and technically advanced solution with the option of repeated use. 📌 Earthworks Active surveying and earthworks have commenced. A new topographic survey of the site has been conducted, earthwork volumes have been recalculated, and villa positions have been staked out. Approximately 6,000 m³ of limestone from the Bloom project quarry has already been delivered to the site — the material is being used to form and stabilize the foundations for subsequent construction stages.
March 2026
🏗 ARAVITA | Report #5 (March 23, 2026) We’re sharing the current construction progress of the Aravita Residence project. Site Preparation — The site has been fully cleared, and all construction and бытовой waste has been removed. — Construction of storage facilities for materials has been completed. Site Setup — The security post, checkpoint, and wheel-washing zone have been completed. — Construction of the sales office is ongoing. Foundation Works The project utilizes a pile (column) foundation system. The construction process is carried out in stages: • First, “footings” (concrete bases for future columns) are installed • Then a blinding layer (lean concrete) is poured • After that, the footings are positioned • Formwork is installed • Finally, pedestal concreting is carried out according to the design dimensions Current Progress Foundation works have begun: ✔️ 32 footings completed 📊 Total planned — 1,234 Next Steps — By the end of the month, we plan to begin earthworks and site layout (setting out). — We will also start installing temporary fencing around the site.
January 2026
🏗 ARAVITA | Report #4 Construction of the on-site warehouse facilities for storing materials and equipment has been completed. At the same time, we have begun building the security post, entrance zone, and wheel-washing station. This will strengthen access control to the site and improve overall organization and cleanliness of the территории. Construction of the marketing office has also started — it will become a truly functional and inspiring space. It will feature: • samples and mood boards of finishing materials for the future villas, • engineering system displays — including manifold collector units and electrical panels that are already being assembled in our MEP laboratory. We are looking forward to the completion of this space — it will become an important part of the project and a key touchpoint for partners and clients. More details — in the video above 👆
Project details
Leasehold — 30 years 9 months
30 years
June 2028
Zona Perumahan (R)
Perumahan Kepadatan Rendah (R-4)
28/41 left
Management Info
Partner management company
15%
6% for null years