Ardhana Residence

A place where memories are born

Contacts

September 2026

Here is the latest update from the ARDHANA construction site. 🏠 Building A Ground Floor: • Masonry works for the restaurant and lobby walls have been completed. • Rough wall finishing works for the restaurant and lobby have been completed. 1st Floor: • Installation of all window frames has been completed. • Finishing works are ongoing. • Ceiling frame installation has been completed. • Installation of decorative gypsum board panels is ongoing. • Bathroom floor and wall tile installation works are ongoing. 2nd Floor: • Installation of all window frames has been completed. • MEP works are ongoing. • Ceiling frame installation has been completed. • Installation of decorative gypsum board wall panels is ongoing. Roof: • Waterproofing works are nearing completion. • Steel roof frame structures have been delivered to the construction site. • Installation of the steel roof frame is scheduled to commence within the next few days. 🏠 Building B Ground Floor: • Construction of the architectural conical columns is nearing completion. • MEP works are ongoing. 1st Floor: • Installation of window frames has been completed. • Installation of steel ceiling frames is nearing completion. • Floor tile installation in the bathrooms has commenced. 2nd Floor: • Wall tile installation in the bathrooms is ongoing. • Installation of window frames has been completed. • MEP works are ongoing. 3rd Floor: • Formwork dismantling for the final floor slab has been completed. • Preparatory works for wall masonry are underway. Roof: • Planter box construction works have commenced. • Preparatory works for waterproofing are underway. ↗️ General Construction Works • Façade tile installation works are ongoing. • Construction of the grease trap for the restaurant is ongoing. • Concreting of the final section of the elevator shaft has been completed. • The final section of the elevator shaft is undergoing the required strength-gain period. 🔥 We will continue to share further updates as construction progresses.

September 2026

ARDHANA | Construction Progress | 02.09.2026 🏗️ 🏢 Building A Ground Floor • Masonry works for the restaurant premises are progressing. First Floor • Window installation is now underway. • Interior finishing works, ceiling installation and decorative gypsum board panel installation are progressing. • Bathroom tiling works are underway. Second Floor • Reinforced concrete sink installation is nearing completion. • MEP works and ceiling installation are progressing. • Installation of decorative gypsum board wall panels has commenced. Roof • Waterproofing works are now underway. • Preparatory works for the installation of the steel roof structure are in progress. 🏢 Building B Ground Floor • Ground-floor slab concreting has been completed. • Construction of the architectural conical columns is nearing completion. First Floor • Window installation is now underway. • Rough floor works within the units and bathroom wall tiling have been completed. • Interior finishing works and rough floor installation in the corridors are progressing. Second Floor • Interior finishing works and reinforced concrete sink installation are progressing. Third Floor • The roof slab has reached the required design strength. • Formwork dismantling is now underway. ⚙️ General Works • Façade tile installation is progressing. • The grease trap for the restaurant is currently under construction. • Construction of the final section of the elevator shaft is progressing.

August 2026

ARDHANA | Construction Progress Update 🏗️ Here is the latest progress update straight from the ARDHANA construction site! 🍽️ Lobby & Restaurant (Building A) 🔹 Ground Floor: • Masonry works for the restaurant premises are nearing completion. 🔹 1st Floor: • Finishing works are ongoing. • Ceiling installation works are ongoing. • Installation of decorative gypsum board panels is ongoing. • Tile installation works in the bathrooms are ongoing. 🔹 2nd Floor: • Construction of reinforced concrete sinks is ongoing. • MEP works are in progress. 🔹 Roof: • Roof columns have achieved the required design strength. • Preparatory works for the installation of the steel roof structure are underway. —————————— 🏢 Main Building (Building B) 🔹 Ground Floor: • Ground floor slab concreting works are nearing completion. • Construction of architectural conical columns is nearing completion. • Water tank construction works have been completed. 🔹 1st Floor: • Rough floor installation works are ongoing. • Wall finishing works are ongoing. • Tile installation works are ongoing. 🔹 2nd Floor: • Rough wall finishing works have been completed. • Finishing works are ongoing. • Construction of reinforced concrete sinks is ongoing. 🔹 3rd Floor: • Floor slab concreting works have been completed. • The floor slab is undergoing the required strength-gain period. —————————— ⚙️ General Construction Works • Façade tile installation works have commenced. • Construction of the grease trap for the restaurant is ongoing. We continue to move forward and will share more updates as construction at ARDHANA progresses! ✨

August 2026

🏗 ARDHANA | Construction Progress Update 📅 06.08.2026 Construction at ARDHANA is progressing according to schedule. Here are the latest updates from the site. Lobby & Restaurant (Building A) Ground Floor • Masonry works for the restaurant premises are nearing completion. 1st Floor • Finishing works are ongoing. • Ceiling installation works are ongoing. • Installation of decorative gypsum board panels is ongoing. • Tile installation works in the bathrooms have commenced. 2nd Floor • Rough finishing works have been completed. • Finishing works have commenced. • MEP works are in progress. Roof • Roof column formwork has been installed. • Reinforcement of the roof columns has been completed. • Roof column concreting is scheduled within the next few days. Main Building Ground Floor • Ground floor slab concreting works are nearing completion. • Construction of architectural conical columns is ongoing. 1st Floor • Rough floor installation works are ongoing. • Wall finishing works are ongoing. 2nd Floor • Masonry works have been completed. • Rough wall finishing works are nearing completion. • Finishing works have commenced. 3rd Floor • Formwork installation and roof slab reinforcement have been completed. • Roof slab concreting is scheduled within the next few days. General Construction Works • Construction of architectural conical façade columns is nearing completion. • Installation of scaffolding for façade tile works has commenced. • The room above the STP has achieved the required design strength. 📌 We will continue to share regular updates as construction at ARDHANA progresses.

July 2026

🏗 ARDHANA · CONSTRUCTION PROGRESS REPORT · 11.07.2026 Here is the latest structural and finishing progress update from the Ardhana construction site: 🏢 BUILDING A • Ground Floor: Masonry works for the restaurant premises are actively ongoing. • 1st Floor: Fine finishing works, ceiling installation, and the mounting of decorative gypsum board panels are underway. • 2nd Floor: Rough finishing works and rough floor installation are ongoing. • Roof: Construction of structural roof columns is in progress. 🏢 BUILDING B • Ground Floor: Ground floor slab pouring and the construction of architectural conical columns are ongoing. • 1st Floor: Rough finishing works are fully completed; rough floor installation is ongoing. • 2nd Floor: Wall masonry is nearing completion, and rough finishing works have successfully commenced. • 3rd Floor: Formwork installation and roof slab reinforcement are underway. 🛠 GENERAL SITE WORKS • Construction of the utility room above the STP (Sewage Treatment Plant) is ongoing. • Civil works have commenced on the balance tank. • Installation of the grease trap has begun. • Engineering teams have commenced the pool axis layout works.

June 2026

🏗️ Construction Site Report | 28.06.2026 Building A • Ground Floor: Masonry works for the restaurant premises have commenced. 🧱 1st Floor: • Finishing works ✨ and ceiling installation are ongoing. • Rough floor installation has been completed. • Installation of decorative gypsum board panels continues. 2nd Floor: Rough finishing works are nearing completion 🏁; rough floor installation is ongoing. • Roof: Construction of the roof columns is currently underway. Building B • Ground Floor: Slab reinforcement works have commenced. ⛓️ Construction of architectural conical columns is ongoing. 🏛️ • 1st Floor: Rough floor installation works are ongoing. • 2nd Floor: Masonry works are ongoing. 🧱 Dismantling of the floor slab formwork is nearing completion. 🛠️ • 3rd Floor: Columns have achieved the required design strength. Formwork installation and roof slab reinforcement are ongoing. 🏗️ General Construction Works • Construction of the columns for the room above the STP (Sewage Treatment Plant) has been completed. • Construction of the balance tank 💧 and grease trap has commenced. • Pool axis layout works have started. 📏

May 2026

🏗️ Site Progress Report | 28.05.2026 Building A Ground Floor Floor slab concreting completed MEP works completed Floor 1 Final finishing in progress Ceiling installation started Subfloor installation started Steel lintels above windows installed RC bases for sink mounting in progress Planter boxes completed Floor 2 Partition walls completed Rough finishing in progress MEP works in progress Building B Ground Floor Additional retaining walls installed Backfilling of retaining wall cavities for terraces completed Architectural tapered columns started Floor 1 MEP works completed Rough finishing of rooms and corridors completed Final finishing in progress RC bases for sink mounting in progress Floor 2 Floor slab formwork dismantling in progress Floor 3 Columns and floor slab concreted Preparatory works for top-floor slab formwork underway 🛠️ General Construction Works Septic tank installation nearing completion Architectural tapered columns installation in progress Concreting of two RC staircases planned for the coming days: Spiral staircase and L-shape staircase

May 2026

Construction Site Report | 06.05.2026 Building A: Ground Floor: •⁠ ⁠MEP works have been completed. 1st Floor: •⁠ ⁠Main MEP works have been completed. •⁠ ⁠Rough finishing works have been completed. •⁠ ⁠Finishing works have commenced. •⁠ ⁠Installation of metal lintels above windows has been completed. •⁠ ⁠Installation of reinforced concrete bases for sink fixtures is in progress. 2nd Floor: •⁠ ⁠Wall partition installation has been completed. •⁠ ⁠Rough wall finishing works have commenced. Rooftop: •⁠ ⁠Rooftop column construction is ongoing. Building B: Ground Floor: •⁠ ⁠Waterproofing of the retaining wall has been completed. •⁠ ⁠Preparatory works for backfilling are in progress. •⁠ ⁠Ground floor slab construction is in progress. •⁠ ⁠MEP works have commenced. 1st Floor: •⁠ ⁠Masonry works have been completed. •⁠ ⁠Rough finishing works are approximately 70% complete. •⁠ ⁠MEP works have been completed. •⁠ ⁠Finishing works have commenced. •⁠ ⁠Installation of reinforced concrete bases for sink fixtures is in progress. 2nd Floor: •⁠ ⁠Columns have achieved the required design strength. •⁠ ⁠Slab concreting is in progress. General Construction Works: •⁠ ⁠Septic tank construction works are nearing completion. •⁠ ⁠Installation of three types of staircases is in progress: one spiral and two L-shaped. •⁠ ⁠Spiral staircase: formwork and reinforcement are approximately 80% complete; concreting is scheduled. •⁠ ⁠L-shaped staircases: formwork installation has commenced.

April 2026

Construction Site Report | 02.04.2026 Building A: 1st Floor: - Rough wall finishing works have commenced - Installation of metal lintels above windows is in progress - Electrical, sewerage and water supply works are in progress 2nd Floor: - Installation of architectural columns is in progress - Masonry works have commenced Rooftop: - Column construction is ongoing Building B: Ground Floor: - Retaining wall construction works are nearing completion (including retaining walls for Buildings A and B) 1st Floor: - Masonry works are nearing completion - Electrical, sewerage and water supply works are ongoing 2nd Floor: - Columns have achieved required design strength 3rd Floor: - Slab construction works are ongoing - Reinforcement and formwork installation are in progress

March 2026

Construction Site Report | 11.03.2026 Building A 1st Floor: • Wall masonry works have been completed • Preparatory works for rough flooring and rough finishing are in progress • Planter box installation is nearing completion 2nd Floor: • Wall masonry works have started • Planter box installation has started Rooftop: • Reinforcement of columns is underway • Column formwork installation is in progress • Surface preparation for waterproofing is being carried out Building B Ground Floor: • Retaining wall construction is nearing completion 1st Floor: • Masonry works are 50% complete 2nd Floor: • Column installation works have been completed 3rd Floor: • Reinforcement of beams and floor slab is in progress

February 2026

Project details

Ownership

Leasehold — 27 years 6 months

Lease extension

30 years, priority

Project handover

September 2027

Villa construction completion

June 2025

Boutique Hotel Construction Completion

September 2027

Permits

PBG

Obtained

SLF

Obtained
Land zone

Zona Perumahan (R)

Land subzone

Perumahan Kepadatan Rendah (R-4)

Total units

45/45 left

Price range
USD90,000 - 510,000

Management Info

Management type

Partner management company

Management fee

10%

Management company change