September 2026
Here is the latest update from the ARDHANA construction site. 🏠 Building A Ground Floor: • Masonry works for the restaurant and lobby walls have been completed. • Rough wall finishing works for the restaurant and lobby have been completed. 1st Floor: • Installation of all window frames has been completed. • Finishing works are ongoing. • Ceiling frame installation has been completed. • Installation of decorative gypsum board panels is ongoing. • Bathroom floor and wall tile installation works are ongoing. 2nd Floor: • Installation of all window frames has been completed. • MEP works are ongoing. • Ceiling frame installation has been completed. • Installation of decorative gypsum board wall panels is ongoing. Roof: • Waterproofing works are nearing completion. • Steel roof frame structures have been delivered to the construction site. • Installation of the steel roof frame is scheduled to commence within the next few days. 🏠 Building B Ground Floor: • Construction of the architectural conical columns is nearing completion. • MEP works are ongoing. 1st Floor: • Installation of window frames has been completed. • Installation of steel ceiling frames is nearing completion. • Floor tile installation in the bathrooms has commenced. 2nd Floor: • Wall tile installation in the bathrooms is ongoing. • Installation of window frames has been completed. • MEP works are ongoing. 3rd Floor: • Formwork dismantling for the final floor slab has been completed. • Preparatory works for wall masonry are underway. Roof: • Planter box construction works have commenced. • Preparatory works for waterproofing are underway. ↗️ General Construction Works • Façade tile installation works are ongoing. • Construction of the grease trap for the restaurant is ongoing. • Concreting of the final section of the elevator shaft has been completed. • The final section of the elevator shaft is undergoing the required strength-gain period. 🔥 We will continue to share further updates as construction progresses.
September 2026
ARDHANA | Construction Progress | 02.09.2026 🏗️ 🏢 Building A Ground Floor • Masonry works for the restaurant premises are progressing. First Floor • Window installation is now underway. • Interior finishing works, ceiling installation and decorative gypsum board panel installation are progressing. • Bathroom tiling works are underway. Second Floor • Reinforced concrete sink installation is nearing completion. • MEP works and ceiling installation are progressing. • Installation of decorative gypsum board wall panels has commenced. Roof • Waterproofing works are now underway. • Preparatory works for the installation of the steel roof structure are in progress. 🏢 Building B Ground Floor • Ground-floor slab concreting has been completed. • Construction of the architectural conical columns is nearing completion. First Floor • Window installation is now underway. • Rough floor works within the units and bathroom wall tiling have been completed. • Interior finishing works and rough floor installation in the corridors are progressing. Second Floor • Interior finishing works and reinforced concrete sink installation are progressing. Third Floor • The roof slab has reached the required design strength. • Formwork dismantling is now underway. ⚙️ General Works • Façade tile installation is progressing. • The grease trap for the restaurant is currently under construction. • Construction of the final section of the elevator shaft is progressing.
August 2026
ARDHANA | Construction Progress Update 🏗️ Here is the latest progress update straight from the ARDHANA construction site! 🍽️ Lobby & Restaurant (Building A) 🔹 Ground Floor: • Masonry works for the restaurant premises are nearing completion. 🔹 1st Floor: • Finishing works are ongoing. • Ceiling installation works are ongoing. • Installation of decorative gypsum board panels is ongoing. • Tile installation works in the bathrooms are ongoing. 🔹 2nd Floor: • Construction of reinforced concrete sinks is ongoing. • MEP works are in progress. 🔹 Roof: • Roof columns have achieved the required design strength. • Preparatory works for the installation of the steel roof structure are underway. —————————— 🏢 Main Building (Building B) 🔹 Ground Floor: • Ground floor slab concreting works are nearing completion. • Construction of architectural conical columns is nearing completion. • Water tank construction works have been completed. 🔹 1st Floor: • Rough floor installation works are ongoing. • Wall finishing works are ongoing. • Tile installation works are ongoing. 🔹 2nd Floor: • Rough wall finishing works have been completed. • Finishing works are ongoing. • Construction of reinforced concrete sinks is ongoing. 🔹 3rd Floor: • Floor slab concreting works have been completed. • The floor slab is undergoing the required strength-gain period. —————————— ⚙️ General Construction Works • Façade tile installation works have commenced. • Construction of the grease trap for the restaurant is ongoing. We continue to move forward and will share more updates as construction at ARDHANA progresses! ✨
August 2026
🏗 ARDHANA | Construction Progress Update 📅 06.08.2026 Construction at ARDHANA is progressing according to schedule. Here are the latest updates from the site. Lobby & Restaurant (Building A) Ground Floor • Masonry works for the restaurant premises are nearing completion. 1st Floor • Finishing works are ongoing. • Ceiling installation works are ongoing. • Installation of decorative gypsum board panels is ongoing. • Tile installation works in the bathrooms have commenced. 2nd Floor • Rough finishing works have been completed. • Finishing works have commenced. • MEP works are in progress. Roof • Roof column formwork has been installed. • Reinforcement of the roof columns has been completed. • Roof column concreting is scheduled within the next few days. Main Building Ground Floor • Ground floor slab concreting works are nearing completion. • Construction of architectural conical columns is ongoing. 1st Floor • Rough floor installation works are ongoing. • Wall finishing works are ongoing. 2nd Floor • Masonry works have been completed. • Rough wall finishing works are nearing completion. • Finishing works have commenced. 3rd Floor • Formwork installation and roof slab reinforcement have been completed. • Roof slab concreting is scheduled within the next few days. General Construction Works • Construction of architectural conical façade columns is nearing completion. • Installation of scaffolding for façade tile works has commenced. • The room above the STP has achieved the required design strength. 📌 We will continue to share regular updates as construction at ARDHANA progresses.
July 2026
🏗 ARDHANA · CONSTRUCTION PROGRESS REPORT · 11.07.2026 Here is the latest structural and finishing progress update from the Ardhana construction site: 🏢 BUILDING A • Ground Floor: Masonry works for the restaurant premises are actively ongoing. • 1st Floor: Fine finishing works, ceiling installation, and the mounting of decorative gypsum board panels are underway. • 2nd Floor: Rough finishing works and rough floor installation are ongoing. • Roof: Construction of structural roof columns is in progress. 🏢 BUILDING B • Ground Floor: Ground floor slab pouring and the construction of architectural conical columns are ongoing. • 1st Floor: Rough finishing works are fully completed; rough floor installation is ongoing. • 2nd Floor: Wall masonry is nearing completion, and rough finishing works have successfully commenced. • 3rd Floor: Formwork installation and roof slab reinforcement are underway. 🛠 GENERAL SITE WORKS • Construction of the utility room above the STP (Sewage Treatment Plant) is ongoing. • Civil works have commenced on the balance tank. • Installation of the grease trap has begun. • Engineering teams have commenced the pool axis layout works.
June 2026
🏗️ Construction Site Report | 28.06.2026 Building A • Ground Floor: Masonry works for the restaurant premises have commenced. 🧱 1st Floor: • Finishing works ✨ and ceiling installation are ongoing. • Rough floor installation has been completed. • Installation of decorative gypsum board panels continues. 2nd Floor: Rough finishing works are nearing completion 🏁; rough floor installation is ongoing. • Roof: Construction of the roof columns is currently underway. Building B • Ground Floor: Slab reinforcement works have commenced. ⛓️ Construction of architectural conical columns is ongoing. 🏛️ • 1st Floor: Rough floor installation works are ongoing. • 2nd Floor: Masonry works are ongoing. 🧱 Dismantling of the floor slab formwork is nearing completion. 🛠️ • 3rd Floor: Columns have achieved the required design strength. Formwork installation and roof slab reinforcement are ongoing. 🏗️ General Construction Works • Construction of the columns for the room above the STP (Sewage Treatment Plant) has been completed. • Construction of the balance tank 💧 and grease trap has commenced. • Pool axis layout works have started. 📏
May 2026
🏗️ Site Progress Report | 28.05.2026 Building A Ground Floor Floor slab concreting completed MEP works completed Floor 1 Final finishing in progress Ceiling installation started Subfloor installation started Steel lintels above windows installed RC bases for sink mounting in progress Planter boxes completed Floor 2 Partition walls completed Rough finishing in progress MEP works in progress Building B Ground Floor Additional retaining walls installed Backfilling of retaining wall cavities for terraces completed Architectural tapered columns started Floor 1 MEP works completed Rough finishing of rooms and corridors completed Final finishing in progress RC bases for sink mounting in progress Floor 2 Floor slab formwork dismantling in progress Floor 3 Columns and floor slab concreted Preparatory works for top-floor slab formwork underway 🛠️ General Construction Works Septic tank installation nearing completion Architectural tapered columns installation in progress Concreting of two RC staircases planned for the coming days: Spiral staircase and L-shape staircase
May 2026
Construction Site Report | 06.05.2026 Building A: Ground Floor: • MEP works have been completed. 1st Floor: • Main MEP works have been completed. • Rough finishing works have been completed. • Finishing works have commenced. • Installation of metal lintels above windows has been completed. • Installation of reinforced concrete bases for sink fixtures is in progress. 2nd Floor: • Wall partition installation has been completed. • Rough wall finishing works have commenced. Rooftop: • Rooftop column construction is ongoing. Building B: Ground Floor: • Waterproofing of the retaining wall has been completed. • Preparatory works for backfilling are in progress. • Ground floor slab construction is in progress. • MEP works have commenced. 1st Floor: • Masonry works have been completed. • Rough finishing works are approximately 70% complete. • MEP works have been completed. • Finishing works have commenced. • Installation of reinforced concrete bases for sink fixtures is in progress. 2nd Floor: • Columns have achieved the required design strength. • Slab concreting is in progress. General Construction Works: • Septic tank construction works are nearing completion. • Installation of three types of staircases is in progress: one spiral and two L-shaped. • Spiral staircase: formwork and reinforcement are approximately 80% complete; concreting is scheduled. • L-shaped staircases: formwork installation has commenced.
April 2026
Construction Site Report | 02.04.2026 Building A: 1st Floor: - Rough wall finishing works have commenced - Installation of metal lintels above windows is in progress - Electrical, sewerage and water supply works are in progress 2nd Floor: - Installation of architectural columns is in progress - Masonry works have commenced Rooftop: - Column construction is ongoing Building B: Ground Floor: - Retaining wall construction works are nearing completion (including retaining walls for Buildings A and B) 1st Floor: - Masonry works are nearing completion - Electrical, sewerage and water supply works are ongoing 2nd Floor: - Columns have achieved required design strength 3rd Floor: - Slab construction works are ongoing - Reinforcement and formwork installation are in progress
March 2026
Construction Site Report | 11.03.2026 Building A 1st Floor: • Wall masonry works have been completed • Preparatory works for rough flooring and rough finishing are in progress • Planter box installation is nearing completion 2nd Floor: • Wall masonry works have started • Planter box installation has started Rooftop: • Reinforcement of columns is underway • Column formwork installation is in progress • Surface preparation for waterproofing is being carried out Building B Ground Floor: • Retaining wall construction is nearing completion 1st Floor: • Masonry works are 50% complete 2nd Floor: • Column installation works have been completed 3rd Floor: • Reinforcement of beams and floor slab is in progress
February 2026









Project details
Leasehold — 27 years 6 months
30 years, priority
September 2027
June 2025
September 2027
PBG
ObtainedSLF
ObtainedZona Perumahan (R)
Perumahan Kepadatan Rendah (R-4)
45/45 left
Management Info
Partner management company
10%