👊 Foundation Works • Earthworks for the first 10 foundations have been completed. • Materials for the first 10 foundations have been purchased and delivered to the site. • Blinding concrete works have been completed. • Formwork installation and reinforcement cage assembly are underway. • In parallel, earthworks continue for the next phase of foundations, along with backfilling of part of the excavation. ↗️ Site Infrastructure • Foundations for the temporary water tanks have been completed, and the tanks have been installed. • The construction office has been installed, and a new floor screed has been completed. • Internal office partitions are being dismantled. The office design is being developed in line with the style of the project’s units. • Finishing materials are being selected so that clients can view and experience them in person before the mock-up unit is completed. 🔥We will continue to share further updates as construction progresses.

August 2026

BLOOM | Project Progress Update ✨ 🗓️ August 14, 2026 Work on BLOOM is progressing across several areas simultaneously: we are finalizing key project solutions while preparing the site for the next stage of construction. Site Works 🏗️ • Earthworks are underway. • Site preparation for foundation works is ongoing. Construction Site Infrastructure • On-site accommodation for the construction team is being built. • The construction site office is being installed. By progressing with project planning and site preparation in parallel, we are creating the foundation for the next stages of BLOOM’s development.

June 2026

Report date: 3 June 2026 Stage: substructure / zero cycle (site preparation, earthworks, temporary utility connections) 📐 1. Geodetic Works Excavation pit boundaries set out on site. As-built survey of the excavated pit completed. Main building axes set out for the continuation of works. 💧 2. Water Supply Connection Technical connection of the construction site to the PDAM water supply network completed. Service lines laid; main inlet shut-off valve and water meter installed. 🚜 3. Earthworks Excavation of the pit completed within design boundaries. Removal of surplus soil from the site is ongoing. ⚡ 4. Temporary Power Supply Connection Enclosure for the meter and temporary power supply equipment erected. Works underway to technically connect the site to the PLN electrical grid. 🏗️ 5. Site Setup and Coordination Contract signed for the site's internet connection; the provider is laying and connecting the cable lines. Outfitting and provisioning of the site continues in line with the approved Site Organization Plan (ПОС). Working meetings held and coordination among project participants carried out. ✅ Overall Project Status Works are progressing in line with the approved schedule. No significant deviations from planned timelines recorded. 📅 Planned Works for the Next Reporting Period Completion of the temporary utility connections. Installation of the blinding concrete (lean-concrete preparation). Assembly of foundation reinforcement cages. Preparation for concrete works.

March 2026

We have begun the first stage of the Bloom Hotel Melasti project implementation. At the construction site, the perimeter fencing has been replaced, security posts have been installed, and excavation works for the foundation pit have commenced. All the details are in the video. This is the beginning of a long journey: ahead is the creation of our design hotel in Bali — a space of aesthetics, inspiration, and the unique atmosphere of Bloom.

Project details

Ownership

Leasehold — 27 years 5 months

Lease extension

30 years, priority

Project handover

September 2028

Permits

PBG

Obtained
Land zone

Zona Pariwisata (W)

Land subzone

Pariwisata (W)

Total units

70/70 left

Price range
USD121,975 - 224,400

Management Info

Management type

Partner management company

Management fee

10%

Management company change

Not allowed

Guaranteed ROI

6% for 8 years

Additional resources